Lessons Learned
Allen Harbor -
Little
Mussachuck - Sachuest
Allen Harbor Marsh Restoration, North
Kingstown
Description | Construction
| Elements of Success and Failure | Benefits
 |
Allen Harbor Navy Davisville/Quonset Landfill in North Kingstown
Courtesy: CRMC |
Description of the Restoration
Allen Harbor is located on the west shore of Narragansett Bay in
North Kingstown. The wetland restoration project took place in conjunction
with the remediation of a U.S. Navy landfill that was used between
1946 and 1972 for the disposal of waste material generated by the
Naval Construction Battalion Center Davisville and Naval Air Station
Quonset Point. Reportedly, municipal type waste, including construction
debris, rubble, preservatives, paint thinners, degreasers, Polychlorinated
Biphenyls (PCB), asbestos, ash, sewerage sludge, 55-gallon drums,
used mineral grit, and fuel oil were placed in the landfill. Foster
Wheeler Environmental Corporation (FWEC) was the Navy’s contractor
for the remediation of the landfill and restoration of the salt
marsh.
The wetland restoration project at Allen Harbor was performed in December 1998
to compensate for wetland areas that were impacted or lost during
the remedial construction activities associated with the Allen Harbor
Landfill project. The areas that were impacted included coastal
wetlands, tidal mud flats, and sub tidal habitats. The U. S. Fish
and Wildlife Service (USFWS) and the Coastal Resources Management
Council (CRMC) calculated the area of compensation to be 1.5 acres.
The wetland restoration project was designed by the USFWS and CRMC and consisted
of replacing a 2-acre area of common reed (Phragmites australis) adjacent to Allen Harbor with salt marsh vegetation.
Construction
The construction of the project included removing all of the Phragmites
in the area and lowering the elevation of the wetland to allow an
increased volume of salt water to flood the area.
 |
Landfill site after capping and stabilization with intertidal marsh grass at base of riprap
Courtesy: CRMC |
Excavation lines and grades were indicated by CRMC on topographic maps provided
by the contractor. A survey was conducted of an existing stream that flows through
the project area to control the location and elevation of the stream during
construction. A floating silt curtain was installed at the discharge point of the
stream to control the migration of sediments into Allen Harbor.
Phragmites and soil removal was performed using a low ground pressure
bulldozer and a Manitowoc 4000W crane. The material was placed in an open field
at Calf Pasture Point that was designated as a disposal site by the permitting
authorities and the contractor.
Elements of Success and
Failure
The wetland restoration occurred because the Navy’s contractor found
additional contamination at the Allen Harbor landfill late in the
project. Removing the contamination impacted delineated wetlands,
tidal mud flats, and subtidal habitat, and it resulted in two acres
of restored salt marsh consisting primarily of smooth
cordgrass (Spartina alterniflora). Because the contractor
was under time constraints and a disposal site was nearby, the entire
restoration took only thirty days to complete.
Benefits of the Restoration
As can be seen here, a healthy stand of smooth cordgrass
resulted from the restoration at Allen Harbor. The Navy, their contractor
FWEC, CRMC, and USFWS were able to ensure that impacts to the habitats
from the contamination removal were remediated and an existing impacted
habitat was restored.
Return to Top
 |
This site was created through a partnership
of the:
Coastal Resources Management Council
Narragansett Bay Estuary Program
Save The Bay®
|
|